Photo credit: www.15min.lt
Energy from Waste
Vilnius Cogeneration Power Plant (VKJ)
The Vilnius Cogeneration Power Plant is one of the most modern energy facilities in the region, generating approximately 40% of the city’s district heating. For this strategically vital project, the UAB Termoizola team was responsible for complex thermal insulation and scaffolding installation. Additionally, we managed the design, procurement, and installation of electric heating systems for technological and auxiliary piping and equipment.
Following the plant's commissioning, UAB Termoizola continues to provide ongoing insulation maintenance and repair services at this facility.
- Client:
- Vilniaus kogeneracinė jėgainė, UAB
- Year:
- 2020–2025; 2025–2028
- Scope of Work:
- Technical insulation and scaffolding. Thermal insulation repair works, including material procurement. Scaffolding erection, rental, and dismantling services.